Raipur: People are forced to live with daily traffic jams at the Mandi Gate railway crossing in Devendra Nagar. On one side, around 150 trains pass through the crossing during the day. On the other, lakhs of people are stuck on the road. A fund of Rs 30 crore is ready to solve the problem and a plan to build an underbridge exists, but construction has not started. The reason is not a shortage of space on the road but approvals tangled in government files. The Mandi Gate underbridge proposal now appears to be stuck in files once again.
According to information, even after the budget approval and the receipt of funds, the Railway has not approved the design for a year. Meanwhile, the Public Works Department (PWD) continues to hold meetings and exchange correspondence. It is also being reported that people from the mandi are not giving land either.
Mandi Gate Underbridge Proposal in Raipur Was Scrapped Earlier After Being Included in 2021-22 Budget
According to information received from the department, the Mandi Gate underbridge proposal was first included in the 2021-22 budget. It was cancelled two years later because approval from the government was not received. Given the growing demand, the PWD had the project included again in the 2025-26 budget. Despite a provision of crores, if the necessary approvals are not received on time, the plan may be shelved this time too.
Raipur Residents Ask When the Wait for Mandi Gate Underbridge Will End
The gate that closes every time a train passes, long queues of vehicles and wasted time have become part of people's daily routine. The question is why the way for the underbridge is not opening when funds are available and the need is clearly visible. People are also asking how long their time and patience will keep being spent in the tussle between departments.
Mandi Gate Railway Crossing in Raipur Stays Shut for More Than 10 Minutes at Times
About 150 to 170 goods and passenger trains pass daily through the Mandi Gate crossing on the Waltair railway line. As soon as the gate closes before a train arrives, a queue of vehicles forms on the road. Often one train follows another, because of which the gate remains closed for more than ten minutes at times. Once the underbridge is built, people in dozens of areas, including Pandri, Mova, Devendra Nagar and Phaphadih, will get relief.